Estimated Project TimelineSomeone just shared on the following estimated schedule on the forum:
Foundation Works (10%) 4Q 2010 – 3Q 2011
Concrete Framework (10%) 1Q 2011 – 3Q 2012
Brick Walls (5%) 3Q 2011 – 4Q 2012
Ceiling (5%) 1Q 2011 – 4Q 2012
Doors, Windows & Wirings (5%) 2Q 2011 – 1Q 2013
Common Area (5%) 1Q 2012 – 1Q 2013
TOP (25%) 1Q 2013 – 3Q 2013